3 Part 3: V-Modell Reference Tailoring
3.7 Decision Gates
3.7.9 System Designed
Purpose
The »Decision Gate »System Designed includes the final evaluation of the capacity of the »System Architecture and the »Enabling System Architecture.
In case of a positive assessment, the »System Specification, the »Logistic Support Specification and the »Evaluation Specification System Element are completed for the system and all designed system elements. The basic implementation, test and integration procedures are specified in the »System Implementation, Integration and Evaluation Concept and the »Enabling System Implementation, Integration, and Evaluation Concept. In addition, a »Evaluation Specification System Element is prepared for each system element. Thus, a following detailed design can be executed within a unit based on a stable preliminary design. In addition, an »External Unit Specification was prepared for external units.
A detailed »Project Plan includes the planning for the following »Project Progress Stage. The »Project Status Report documents the project progress, and the »Quality Status Report describes the quality characteristics of the project. In addition, the hazards connected with the project are documented in a »Safety and Security Analysis.
A »Project Progress Decision will be made in order to proceed to the next decision gate.