3 Part 3: V-Modell Reference Tailoring
3.7 Decision Gates
3.7.14 Project Progress Revised
|
Products: |
Project Progress Decision, Project Status Report (Supplier), Project Plan, Project Status Report, Quality Status Report |
Purpose
At the decision gate Project Progress Revised, the Acquirer checks the project progress achieved by the Supplier. While the Supplier deals with the system development, the Acquirer is tasked with supporting the Supplier in technical questions and observing the project progress.
The schedule of this decision gate will be planned in dependence on the Supplier. The Supplier submits the Project Status Report (Supplier) as decision basis for this decision gate.
A detailed »Project Plan includes the planning for the following »Project Progress Stage. The »Project Status Report documents the project progress, and the »Quality Status Report describes the quality characteristics of the project.
A »Project Progress Decision will be made in order to proceed to the next decision gate.