5.5.32 Planning of Risk Management Measures

Content-dependent Work Products:

Project Plan, Risk List, Project Manual, Project Status Report

The planned risk management measures (see the »Risk Mitigation Measures) are documented in the action plan of the »Risk List. The measures that are initiated are determined according to the specifications of the topic »Risk Management - Organization and Directives in the »Project Manual. All initiated measures have to be included in the project plan. In addition, the »Project Status Report includes a summary of the measures intended to reduce the identified risks