5 Part 5: V-Modell Reference Work Products
5.5 Content-Related Product Dependencies
5.5.31 Consistency of Work Orders and Project Plan
|
Content-dependent Work Products: |
Task description, deadlines and funding for a »Work Order may be taken from the »Project Plan, i. e. work orders are also scheduled in the »Project Plan.
If during the basic ordering agreement the »Project Leader and the team members come to the conclusion that the deadlines, expenditures and resources contained in the »Project Plan cannot be realized, the »Project Plan has to be revised.