3 Part 3: V-Modell Reference Tailoring

3.7 Decision Gates

3.7.13 Delivery Conducted

Products:

Delivery, Project Progress Decision, Evaluation Report Document, Evaluation Report System Element, Project Plan, Project Status Report, Quality Status Report

Purpose

The »Decision Gate »Delivery Conducted is intended to deliver the system to the acquirer or the user. For this purpose the system or the documents to be delivered will be evaluated, and the result will be recorded in the product »Evaluation Report System Element or the »Evaluation Report Document.

In case of a positive assessment, the (sub-)system shall delivered as »Delivery to the acquirer or user, who can then examine whether the (sub-)system fulfills his/her requirements.

A detailed »Project Plan includes the planning for the following »Project Progress Stage. The »Project Status Report documents the project progress, and the »Quality Status Report describes the quality characteristics of the project.

A »Project Progress Decision will be made in order to proceed to the next decision gate.