3 Part 3: V-Modell Reference Tailoring
3.7 Decision Gates
3.7.1 Project Approved
|
Products: |
Proposal for the Introduction and Maintenance of an Organization-Specific Process Model, Assessment of Request for Proposal, Project Proposal, Project Progress Decision |
Purpose
At the »Decision Gate »Project Approved, the »Steering Committee of the acquirer decides - based on the »Project Proposal - whether the project should be started with the »Request for Proposal.
The Management Board of the supplier decides - based on the »Assessment of Request for Proposal - whether an »Offer should be prepared.
If the project deals with the introduction and maintenance of an organization-specific process model, the »Steering Committee decides - based on the »Proposal for the Introduction and Maintenance of an Organization-Specific Process Model - whether the project should be started with the »Assessment of a Process Model.
A »Project Progress Decision will be made in order to proceed to the next decision gate.